Rambler ATL Construction Update: March 2025

By Annabelle

The Rambler construction team has continued to make steady strides, keeping the project on track for the scheduled August 2025 move-in date.

This month, we are providing updates on the following:

Exterior

Exterior work continues with sidewalk pouring now underway on the north elevation. Finishing touches are being applied to the building’s exterior, including curb installations and continued site power and lighting conduit work.

exterior of Rambler Atlanta

Rambler exterior as of March 2025.

Rambler Atlanta privacy patio screens

Patio privacy screens on Level 3.

Interior and Units

Inside, construction is advancing throughout the building. Drywall installation is nearly complete, as teams focus on painting, trim installation, and the installation of key unit features such as backsplashes, countertops and flooring. 

carpet installation in rambler atlanta hallways

Carpet installation underway in hallways.

Kitchen in Watercolor floor plan at Rambler Atlanta.

Kitchen in Watercolor floor plan at Rambler Atlanta.

interior of a room at rambler atlanta

Interior of a room in Rambler Atlanta.

Closet inside the Proper floor plan at Rambler Atlanta. 

Closet inside the Proper floor plan at Rambler Atlanta.

bathroom at Rambler Atlanta

Bathroom at Rambler Atlanta.

Laundry room inside the Biltmore floor plan at Rambler Atlanta.

Laundry room inside the Biltmore floor plan at Rambler Atlanta.

Blinds installed on a unit on Level 10.

Blinds installed on a unit on Level 10.

View from Rambler Atlanta balcony.

The interiors are moving closer to completion as work progresses through various levels of the building.

Amenity Areas

Restroom and café tile installations are now in place on Level 1, and the first coat of paint has been applied to common areas and the fitness center.

The amenity spaces are taking shape, with a focus on finishing high-traffic areas such as the yoga studio, pool, lobby and the fitness center. Electrical and mechanical ceiling trim work is wrapping up, and installation fixtures in the spa and pool areas are underway.

Sauna framing and blocking on Level 19.

Sauna framing and blocking on Level 19.

Pool deck trellis and lighting being installed on level 19.

Pool deck trellis and lighting being installed on level 19.

Pool deck views as construction nears completion.

Pool deck views as construction nears completion.

Paint begins on study mezzanine.

Paint begins on study mezzanine.

Unit Walkthroughs

Check out the progress on our units by watching our walkthroughs below!

We’re excited to see everything coming together and will provide more updates as the project progresses. If you have any questions, don’t hesitate to reach out to our leasing team.

Stay tuned for more updates next month!

Annabelle

Annabelle is one of Rambler's Marketing Interns; she is a Business major at Georgia Tech with a love for all things creative. Her go-to Daydreamer order is an iced lavender matcha.

March 24, 2025

Get email updates

Be the first to know about exclusive events, construction progress, promos, and more.